The text on this page has been created from Hansard archive content, it may contain typographical errors.
16.
Mr. Manningham-Buller
asked the Secretary of State for War what amount has been expended on the construction of the Ordnance Depot at Bicester since 1945; and what is the estimated future expenditure on construction.
Mr. Shinwell
Approximately £21,000 has been spent on new temporary works at this depot since October, 1945, and £163,000 on maintenance. What expenditure will be incurred in future cannot yet be accurately estimated.
Mr. Manningham-Buller
Can the right hon. Gentleman give an assurance that existing and old established Ordnance Depots, like that at Weedon are being fully utilised, and not left partly unused while this big depot is being expanded?
Mr. Shinwell
That is a matter to be considered in relation to the general reorganisation. I cannot pronounce upon that at present.