Glasgow-Kilmarnock Road

Volume 656: debated on Wednesday 28 March 1962

The text on this page has been created from Hansard archive content, it may contain typographical errors.

28.

asked the Secretary of State for Scotland when work started on the Glasgow-Kilmarnock road; and when it will be completed.

Work on improvement of this road from Eastwood Toll to Malletsheugh, including the reconstruction of Whitecraigs railway bridge, started in November, 1959, and is expected to be completed in September, 1962.