71.

asked the Minister of Transport whether he is aware of the traffic chaos at the Ferrybridge-Knottingley roundabout being constructed at the A.1/A.645; and whether he will expedite the building of the flyover as a matter of urgency.

Works of this nature are bound to cause traffic difficulties. Fresh arrangements for the completion of the project are being considered urgently in consequence of the appointment of a receiver and manager for the affairs of the contractor. The need for expeditious completion of the flyover will be borne in mind.