M4 (Statutory Procedures)

Volume 720: debated on Thursday 11 November 1965

The text on this page has been created from Hansard archive content, it may contain typographical errors.

(Richmond, Surrey), asked the Minister of Transport, when the statutory procedures will be completed for the line of the M.4 motorway.

I am anxious that they should be completed as soon as possible and I hope to publish all the remaining draft Schemes by mid-1966. I cannot forecast the rate of progress thereafter, which will depend on the number and weight of objections, but the procedures cannot normally be completed in less than two years from publication of the draft Scheme.