The text on this page has been created from Hansard archive content, it may contain typographical errors.
Mr. Ian Stewart
asked the Secretary of State for the Environment when he expects that work on the new Barnet bypass section of the Al at Bignells Corner will now be completed; and what are the reasons for the delay.
Mr. Carmichael
The contract for this scheme provided for its completion in November 1974, but, owing to delays occasioned by the three-day working week in the early part of last year and bad weather in the summer and autumn, the contract period was extended to March 1975. The contractor has now requested a further extension and this is being considered.