Offshore Oil Rigs

Volume 893: debated on Monday 16 June 1975

The text on this page has been created from Hansard archive content, it may contain typographical errors.

asked the Secretary of State for Energy what is the annual capacity of the United Kingdom for manufacturing North Sea oil rigs.

Six contractors are currently engaged in the production of 10 platforms. In addition, one concrete platform site is being developed at Portavadie and four other sites have planning permission.

asked the Secretary of State for Energy how many oil rigs for the North Sea are currently under construction in the United Kingdom. and where.

Ten oil production platforms are currently under construction in the United Kingdom as follows:

Steel Platforms
Constructor and SiteNo. being built
Highlands Fabricators, Nigg Bay2
McDermott Scotland Ltd., Ardersier2
RDL (North Sea) Ltd., Methil1
John Laing Construction Ltd., Graythorp2
Concrete Platforms
McAlpine, Ardyne Point2
Howard Doris, Kishorn1
10

asked the Secretary of State for Energy what information he has as to the extent to which United Kingdom-manufactured oil rigs are competitive with those currently being constructed in EEC countries.

To be successful, competitive tenders must be based on price, quality and delivery, and the 10 oil production platform orders won by the United Kingdom have been successful on these criteria against competition from other EEC countries. At present only three oil production platforms for the United Kingdom sector of the North Sea are being constructed elsewhere in the EEC.