asked the Secretary of State for Scotland if he will list in the Official Report the names, date of start and date of completion, where appropriate, of all power stations constructed or under construction since 1960 by the SSEB.

The names, date of start and date of completion, where appropriate, of the South of Scotland Electricity Board power stations in question are listed below:

Name of StationStart on siteDate of completion
Conventional Steam Stations
Kincardine19551963
Cockenzie19621968
Methil19621966
Longannet19641971
Inverkip1970Not yet completed
Nuclear Stations
Hunterston "A"19571964
Hunterston "B"1967Not yet completed
Main Gas Turbines
Clyde's Mill19631965
Dunfermline19631965