Nuclear Reactors

Volume 931: debated on Monday 9 May 1977

The text on this page has been created from Hansard archive content, it may contain typographical errors.

asked the Secretary of State for Energy if he will list the reactors including prototypes at nuclear power stations which have already been installed or authorised, giving the type,

I MAGNOX
Date CommissionedDeclared Station Net Capability
Site1st Reactor2nd Reactor (MWSO)
Berkeley19621962276
Brad well19621962250
Dungeness A19651965410
Hinkley Point A19651965460
Hunterston A19641964300
Oldbury-on-Severn19671968416
Sizewell A19661966420
Trawsfynydd19651965390
Wylfa19711971840
II AGR
Date Commissioned/Estimated Commissioning DateNominal Station
Site1st Reactor2nd ReactorCapacity (MW)
Hinkley Point BSeptember 1976Mid 19771,320
Hunterston BFebruary 1976*March 1977*1,320
Dungeness BLate 1978Early 19791,200
HartlepoolEarly 1979Late 19791,320
HeyshamMid 1979Late 19791,320
* These dates refer to synchronisation with the grid, which is the statistic used by the SSEB. Comparable dates for Hinkley Point B are February 1976 and October 1976.
The following reactors have been installed in stations operated by AEA and BNFL:
TypeNumber of ReactorsOperatorSiteDate of Start-upGross Capacity (MW)
Magnox4BNFLCalderHall.1956 (2 reactors) 1958–1959 (2 reactors)240
Magnox4BNFLChapelcross.1958–1959240
AGR1AEAWindscale196233
SGHWR1AEAWinfrith1967100
PFR1AEADounreay1975250
The Government are reviewing thermal reactor choice for future orders.