Roads (Construction And Maintenance)

Volume 973: debated on Thursday 15 November 1979

The text on this page has been created from Hansard archive content, it may contain typographical errors.

asked the Minister of Transport of he will list in the Official Report

SchemePre-tender estimate £ millionAccepted tender £ million
A1 Felton By-Pass, Stage 2A1·61·7
A2 Canterbury By-Pass9·48·9
A6 Silsoe By-Pass1·41·4
A13 Mar Dyke-East of Grays16·718·4
A19 Billingham Diversion—Earthworks3·91·9
A27 Portsbridge-Broadmarsh Improvement2·32·0
A30 Billet Bridge-Avondale Road0·60·6
A34 Whitchurch-Litchfleld Improvement2·02·1
A45 Ipswich By-Pass (Orwell Bridge)23·623·6
A47 Swaffham By-Pass3·13·4
A56 Haslingden By-Pass10·410·8
A65 Skipton By-Passes10·510·2
A66 Stockton-Thornaby12·310·4
A66 Appleby By-Pass6·56·6
A590 Meathop-Sampool Bridge7·46·0
A604 Bar Hill·Godmanchester8·38·1
A1079 Beverley By-Pass7·88·0
M25 Chertsey-Wisley: New Haw Viaduct3·53·7
M25 A111-A1017·115·8
M25 Egham-Yeoveney8·96·4
M63 Stockport East/West By-Pass, Stage 27·76·1
M25 A13-A12, Stage 28·17·2
Note: The pre-tender estimates listed above correspond in coverage to the tender; they exclude contingency allowances, land, and ancillary items included in estimates of total cost. The contracts covered are those for schemes in the national trunk road programme costing more than £0·5 million.

asked the Minister of Transport what are the factors used to revalue 1978 survey prices to 1979 survey prices for trunk road construction, trunk road maintenance, local road construction and local road maintenance for each of the years of the period of the forthcoming public expenditure survey.

The following factors have been used to revalue these programmes:

1978 survey prices to 1979 survey prices
Motorway and trunk road construction:
Roads output price index1·092
Land cost index1·296
Local Road Construction:
Tender price index1·165
Cost outturn index1·089
Land cost index1·296
Motorway and trunk road maintenance1·089
Local Road Maintenance1·112
Because the mix of expenditure between land, work in progress and new works, varies from year to year, the overall effect of the revaluation can differ as between one year and another even though the same underlying factors have been used.

his Department's pre-tender estimates of the prices for each trunk road contract let so far in 1979, together with the actual price of the accepted tender.