Mr. George Gardiner
asked the Secretary of State for Transport what progress has been made on the sections of the proposed M25 between Reigate and the M4, and what are the latest target dates for completion.
Mrs. Chalker
[pursuant to her reply, 19 April 1932, c. 49.]: A continuous stretch of 14 miles between the A3 near Wisley and the Heathrow airport spur is already open or under construction. I hope that the difficulties in completing the statutory procedures on the remaining lengths are nearly at an end, and that they will all be under construction by the spring of next year. The target completion dates are:
Reigate—Leatherhead | 1985 |
Leatherhead—Wisley | 1984 |
Wisley—Chertsey | Autumn 1983 |
(Chertsey—Yeoveney | Open) |
Yeoveney—Airport Spur | Spring 1983 |
Airport Spur—M4 | 1985 |