Dornoch Firth Crossing

Volume 33: debated on Monday 6 December 1982

The text on this page has been created from Hansard archive content, it may contain typographical errors.

asked the Secretary of State for Scotland what progress he has made in the preparatory work for the Dornoch Firth crossing; if the design work is complete; and when he expects construction work to begin.

There were objections to draft line of road orders made public last year, and revised proposals will be published once soil investigations have been carried out. Detailed design must await the making of orders.The trunk road programme is currently under review, and the case for an early start on this project has to be judged against the claims of other schemes elsewhere in Scotland. However, the design and procedural work involved is such that, even with the highest priority for money within the programme, the earliest possible financial year for a start of construction would be 1985–86.