Roads (Construction)

Volume 33: debated on Tuesday 7 December 1982

The text on this page has been created from Hansard archive content, it may contain typographical errors.

asked the Secretary of State for Wales if he will list those bypasses or trunk roads in Wales which have not yet had work commenced on them but which are in the firm road programme, together with the latest estimated commencement date for each project.

Details of bypass schemes included in the trunk road programme, together with an indication of possible start dates, will be given in the next edition of "Roads in Wales", which I expect to be available early in the new year.

asked the Secretary of State for Wales if he will list the bypasses currently being built on trunk roads in Wales, the date at which each is expected to be completed, and the cost of each such project.

There is no precise definition of the term "bypass", but schemes which I would consider falling in that category currently under construction are as follows:

Cost £ millionCompletion
Gwynedd
A55/A5—Bangor Bypass241984
A5—Llanfair PG Bypass7·91983
Clwyd
A55—Hawarden Bypass24·41984
A55—Llanddulas-Glan Conwy (COLCON 1)119·61985
S. Glam
A4232—Culverhouse Cross-Capel Llanilltern151984
Mid Glam
A470—Abercynon-Pentrebach45·91985
Dyfed
A477—Kilgetty-Stepaside Bypass71984
A40/A48—Carmarthen Southern Bypass16·51984
Powys
A470/A489—Cemmaes Road Improvement0·71983