M25 And M20

Volume 35: debated on Wednesday 26 January 1983

The text on this page has been created from Hansard archive content, it may contain typographical errors.

asked the Secretary of State for Transport if he will give the latest estimated completion dates for all the outstanding sections of the M25 and M20 motorways for which a line has been fixed.

Depending on completion of statutory procedures, the estimated opening dates for outstanding sections of the M25 are as follows:

SectionEstimated Opening Date
Heathrow airport spur - M4Summer 1985*
M4 - M40Summer 1985*
M40 - Maple CrossSpring 1985
Micklefleld Green - South MimmsSummer 1986
A10 - M11Winter 1983
Mil - A12-A127Spring/Summer 1983
Swanley - SevenoaksWinter 1985
Reigate - LeatherheadSpring 1985
Leatherhead InterchangeSpring 1985
Leatherhead - WisleySpring 1985
Wisley - ChertseyWinter 1983
* Complete M4 interchange Spring 1986.
Work on the M20 (Maidstone - Ashford section is temporarily suspended, but I an currently considering the prospects for its revival.