Mr. Peter Bruinvels
asked the Secretary of State for Transport if he will now give the expected opening dates of the M25, Reigate to Wisley sections, and all other remaining stages of the M25; and if he will make a statement.
Mrs. Chalker
We expect to have the whole of the M25 open to traffic by the end of 1986. The actual opening dates of the remaining sections will depend on the progress made by individual contractors which in turn is influenced by weather and ground conditions.The expected opening dates for these unfinished sections are as follows:
Dates | |
Wisley-Leatherhead | August 1985 |
Leatherhead-Reigate | August 1985 |
Leatherhead Interchange | Partly open already but will come into full use August 1985 |
Poyle-M4 | September 1985 |
M4–M40 | September 1985 |
M4 Interchange | June 1986 |
Swanley-Sevenoaks | July 1986 |
Micklefield Green-Bedmond Road | October 1986 |
Bedmond Road-A405 | October 1986 |
A405-The Bell (A6) | November 1986 |
The Bell-A1 (South Mimms) | November 1986 |