M25

Volume 83: debated on Thursday 25 July 1985

The text on this page has been created from Hansard archive content, it may contain typographical errors.

asked the Secretary of State for Transport if he will now give the expected opening dates of the M25, Reigate to Wisley sections, and all other remaining stages of the M25; and if he will make a statement.

We expect to have the whole of the M25 open to traffic by the end of 1986. The actual opening dates of the remaining sections will depend on the progress made by individual contractors which in turn is influenced by weather and ground conditions.The expected opening dates for these unfinished sections are as follows:

Dates
Wisley-LeatherheadAugust 1985
Leatherhead-ReigateAugust 1985
Leatherhead InterchangePartly open already but will come into full use August 1985
Poyle-M4September 1985
M4–M40September 1985
M4 InterchangeJune 1986
Swanley-SevenoaksJuly 1986
Micklefield Green-Bedmond RoadOctober 1986
Bedmond Road-A405October 1986
A405-The Bell (A6)November 1986
The Bell-A1 (South Mimms)November 1986