The text on this page has been created from Hansard archive content, it may contain typographical errors.

asked the Secretary of State for Defence what parts of the refit programme for HMS Otter and HMS Euryalus which were originally to be carried out by the contractor have been subsequently carried out by naval personnel.

No part of the refit of HMS Otter, originally to be carried out by the contractor, has subsequently been carried out by naval personnel. Only two small items of the refit programme for HMS Euryalus forming part of the original contract—repacking a valve and cleaning a gauge glass—have been carried out by naval personnel. Appropriate adjustments will be made for payments for this work.

asked the Secretary of State for Defence (1) what was the original cost of the refit contract to HMS Euryalus;(2) what was the original cost of the refit contract to HMS Otter;(3) what is the latest estimated cost of the refit contracts for HMS Otter and HMS Euryalus.

Local authority district1983–841984–85
Entrants*CompletionsEntrants*Completions
Mode AMode BMode AMode BMode AMode BMode AMode B
Basingstoke7572784268216834147
East Hampshire2074282473810411
Eastleigh28852173632817915
Fareham405131275289021927
Gosport278622655314536
Hart51012252118356
Havant48694165198625430
New Forest3541234223239617334
Portsmouth1,11164591531,275422531170
Rushmoor21130261572923
Southampton1,4223974431,75027959292
Test Valley288366298914513
Winchester41920412834712121738
Hampshire Total6,5462,316193787,1331,4623,092592
* The entrants figures include a number of young people who have joined more than one youth training scheme.
The figures quoted for completions exclude young peole who left schemes before completing their full entitlement to training.

asked the Secretary of State for Defence what were the original dates for the completion of the refit contracts for HMS Otter and HMS Euryalus; and what are now the expected completion dates.

HMS Euryalus is shortly to complete her refit, which will have taken 48 weeks. This is seven weeks more than the original planned time, but includes four weeks addition for further work added after planning. Work on HMS Otter started in December 1984 with a planned duration of about two years. This remains the case.