Mr. David Marshall
asked the Secretary of State for Scotland if he will list all the motorway and trunk road construction contracts with a works cost of £1 million or more which his Department intends to award in 1987–88, showing in each case the total value of the contract and the expenditure likely to be incurred in that year.
Mr. Ancram
Contracts for the following major schemes, each estimated to cost over £1 million, are expected to be let in 1987–88:
Estimated Total Cost1 £ million | ||
A7 | Middleton Bypass | 1·9 |
A75 | Castle Douglas Bypass | 3·9 |
A75 | Glenluce Bypass | 3·8 |
A77 | Balsalloch to Balcreuchan | 3·8 |
M8 | Starlaw Junction, Livingston | 1·8 |
M80 | Stepps Bypass (Advance Works) | 5·1 |
A82 | Auchendennan to Arden (Loch Lomond) | 1·7 |
A82 | Luss to Camus Nan Clais (Loch Lomond) | 7·5 |
A830 | Polnish to Lochailort | 2·5 |
A9 | Dornoch Firth Approach Roads (South) | 6·0 |
A9 | Dornoch Firth Approach Roads (North) | 2·5 |
A9 | Dunbeath Bridge | 3·1 |
A92 | East Fife Regional Road, Stage III | 12·2 |
A92 | East Fife Regional Road, Stage IV | 5·1 |
A92 | Ellon Bypass | 3·7 |
A92 | Tipperty | 2·2 |
A94 | Candy to Stonehaven | 3·0 |
1 Includes works, land and professional fees. |