Skip to main content

A2

Volume 169: debated on Tuesday 13 March 1990

The text on this page has been created from Hansard archive content, it may contain typographical errors.

To ask the Secretary of State for Transport what is the likely timetable for implementation of the proposal to dual the A2 road between Lydden and Dover.

[holding answer 12 March 1990]: It is too early to forecast the timing of construction of the A2 Lydden (B2060)-Dover improvement scheme which has only just entered the national trunk road programme. Detailed programmes have not yet been prepared. Meanwhile the roads report, "Trunk Roads, England—Into The 1990s", shows "Preferred Route" as the next key preparation stage, with a target date of 1993. This would be followed by detailed design work, leading to publication of formal draft order proposals under the Highways Act.The first step will be the appointment of design agents to work up options.