To ask the Secretary of State for Transport what improvements to the A13 between the North Circular road and Butcher row are currently being undertaken; at what cost; and when they will be completed.

Departmental schemes currently under construction are:

SchemeWorks cost £ millionEstimated date of completion
Leamouth Road Junction Interim Scheme2·0Mid 1991
West India Dock Road Junction Advance statutory undertaker's works3·1Late 1991
The following schemes are due to start this year:

SchemeWorks cost £ millionEstimated date of completion
West India Dock Road Junction phase 11·2Spring 1992
Canning Town Flyover/Ironbridge widening Advanced Works phase 1 Bridge over A1020·5Late 1991
Other schemes in preparation are:

Works cost £ millionEstimated date of completion
Cotton Street/Blackwall Tunnel3·51994
West India Dock Road Junction phase 20·61993
Butcher Row Junction0·71993
Canning Town Flyover/Ironbridge widening Advance works phase 29·21993
Canning Town Flyover/Ironbridge widening21·01997
A13/A112 Junction Improvement44·41996
A13/A117 Junction Improvment35·61995
Progress on some of these schemes will be dependent on the completion of statutory processes which could be subject to public inquiry. Completion dates are therefore provisional.