The text on this page has been created from Hansard archive content, it may contain typographical errors.
18.
Mr. Paice
To ask the Secretary of State for Transport when he expects the dualling of the A11 between Newmarket and Four Wentways to be completed.
Mr. Chope
Tenders for the work were received on 4 February. Assessment, award of contract and mobilisation of the successful contractor normally take about two months. The period for completion in the tender documents is two years, which means the road would be dualled by spring 1993.