Dr. Julian Lewis
To ask the Secretary of State for Defence if he will list the S and T class submarines which (a) have completed, (b) are undergoing and (c) will in future undergo major upgrades together with the (i) completion and (ii) due completion dates in each case. [98241]
Mr. Ingram
Upgrades to S and T class submarines are generally undertaken during docking periods of maintenance lasting six months or during major refit and refuel periods lasting three years. These are known as Upkeep Periods. All S and T Class submarines will undergo a number of Upkeep Periods throughout their lives, and those whose last Upkeep Period included an upgrade, and which are not currently undergoing an Upkeep Period are:
Submarine | Completion date1 |
HMS Splendid | Spring 1998 |
HMS Superb | Summer 1998 |
HMS Tireless | Summer 1999 |
HMS Triumph | Winter 1999 |
HMS Trafalgar | Summer 2000 |
HMS Turbulent | Spring 2002 |
HMS Sovereign | Autumn 2002 |
HMS Torbay | Winter 2002 |
1Dates shown are when the submarine rejoined the fleet. |