To ask the Secretary of State for Transport what the (a) original estimated cost of and (b) most recent cost estimates are for (i) Highways Agency schemes in the Targeted Programme of Improvements and (ii) all local authority schemes approved through the local transport plans. (86139)

For Highways Agency schemes, I refer the hon. Member to my answer today to the hon. Member for Brent, East (Sarah Teather).

I have placed information relating to major local authority schemes (generally those over £5 million) in the Library.

To ask the Secretary of State for Transport which road schemes were commenced by the Highways Agency in the Eastern Region in each year from 1999-2000 to 2005-06; and what the (a) original estimated cost, (b) final outturn cost, (c) original completion date and (d) actual completion date was of each project. (87432)

The following table lists all major road schemes, located in the Eastern Region, that have started works each year since 2000-01. In addition to the major projects detailed, the Highways Agency delivers many maintenance and smaller scheme improvements costing less than £5 million. The Highways Agency does not hold information for these schemes in the requested format.

Scheme

TPI entry cost (£ million)

Total estimated (£ million)

Projected completion date at TPI entry

Actual/latest estimated completion date

Schemes starting construction in 2000-01

A6 Clapham Bypass

31

44

2002-03

December 2002

A11 Roudham Heath-Attleborough improvement

27

50

2002-03

March 2003

Schemes starting construction in 2001-02

A120 Stansted-Braintree improvement

92

105

2004-05

July 2004

Schemes starting construction in 2002-03

A10 Wadesmill-Colliers End

24

40

2003-04

October 2004

Schemes starting construction in 2003-04

None

Schemes starting construction in 2004-05

A14 Rookery Crossroads

5

14

2004-05

March 2006

A47 Thorney Bypass

15

25

2008-09

December 2005

A421 Great Barford Bypass1

25

58

2004-05

August 2006

Schemes starting construction in 2005-06

A11 Attleborough Bypass1

14

29

2007-08

2006-07

M1 J6A-10 Widening1

241

289

2007-08

2008-09

A428 Caxton Common to Hardwick improvement1

22

55

2006-07

2007-08

1 Under construction

This information is not available for the A1 Tempsford Junction improvement as it is not a scheme within the Targeted Programme Improvements. It was, however, the only other major scheme in the Eastern Region, to have started works since 1999-2000. This scheme was completed in October 2001.