To ask the Secretary of State for International Development which information technology projects are being undertaken by (a) his Department and (b) its agencies; what the (i) start date, (ii) original planned completion date, (iii) expected completion date, (iv) originally planned costs and (v) estimated costs are of each; and if he will make a statement. (95869)

DFID is currently undertaking three major IT projects.

The contract for the Quest Electronic Document and Records Management project was signed in March 2004. The main rollout was originally estimated to be completed in December 2005. Detailed planning carried out in early 2005 led to a revised target date of March 2006, which was met. The projected supplier base cost at tender was £8.98 million. The projected total supplier cost is now £11.52 million, which includes implementation of a number of options available under the original contract but not included in the base cost.

The contract for the ARIES Finance, Procurement and Reporting System was signed in November 2005. The rollout is estimated to be complete by October 2008. The projected supplier base cost at tender was £11 million. A number of additional cost options are available under the contract. The ARIES project is currently on track to deliver to time and budget.

The HR Transformation project was initiated in March 2005 and has a budget of £6.5 million. It is primarily a business change project but it includes enhancements to the existing HR system and a number of smaller IT enabled components. The planned completion date is the March 2008. The project is currently on track to deliver to time and budget.