The following information refers to the Northern Ireland Office (NIO) only. It does not include information for its Agencies, NDPBs or the 11 Departments of the Northern Ireland Administration.
The question refers to the 20 largest procurement projects, however these are the only procurement projects that have been initiated since 1997. In some cases the information is not available, such as when completed and final cost of each project. There are several IT projects within Public Prosecution Service for which information could be provided only at disproportionate costs as the data are not readily available.
Causeway Programme (IT)
(a) Original budget: £43,178,105 (£27,374.000—procurement costs)
(b) Cost to date: £23,279,792
(c) Consultancy fees: £2,345,947
FSNI New Accommodation Project (2004)
(a) Original budget: £26,000,000
(b) Cost to date: £326,000
(c) Consultancy fees: £124,000
Regional Office Accommodation—Ballymena, Omagh and Lisburn (2005)
(a) Original budget: £19,889,000 (include all running costs over 15 years)
(b) Cost to date: £3,169,345
(c) Consultancy fees: £519,740
Expected completion July 2008
Final cost estimated £19,889,000
Juvenile Justice Centre Project (2003)
(a) Original budget: £19.2 million (includes construction contract of £16.8 million)
(b) Cost to date: £17.4 million (construction cost as at building handover January 2007)
(c) Consultancy fees: £1.5 million
Not completed yet.
Belfast Office Accommodation (2006)
(a) Original budget: £9,976,836 (include all running costs over 15 years)
(b) Cost to date: £1,407,896
(c) Consultancy fees: £115,575
Expected completion October 2007
Final cost estimated £9,976,836
New Mortuary Project (2004)
(a) Original budget: £4,865,000
(b) Cost to date: £595,000
(c) Consultancy fees: £9,000
Flax (IT) (2003)
(a) Original budget: £8.5 million
Final cost—£8.5 million
Employment Checking Project (2007)
(a) Original budget: £2,415,000
(b) Cost to date: £436,000
(c) Consultancy fees: Nil
Completion—Ongoing
Oasis Refresh (1999)
(a) Original budget: £2.2 million
Final cost £2.2 million
Employment Checking Project (2006)
(a) Original budget: £154,000
(b) Cost to date: £129,000
(c) Consultancy fees: £2,000
Initial Review on Way Forward
(a) Original budget: Not Known
(b) Cost to date: £13,038
(c) Consultancy fees: £13,038