Afghanistan: Peace Keeping Operations

Volume 460: debated on Wednesday 9 May 2007

To ask the Secretary of State for Defence what progress is being made on reconstruction works in Afghanistan being undertaken by those responsible to him. (132266)

The Secretary of State announced the deployment of additional Royal Engineers on 10 July 2006 to accelerate the reconstruction effort in southern Afghanistan. It is worth noting, though, that the UK task force as a whole is deployed to provide security so that reconstruction and development may take place.

The following tables list quick impact projects being undertaken in Helmand Province, and the progress that has been made to date. I have stated the agency responsible for the implementation of each project, and identified whether the responsible agency reports to the MOD. It is important to note, however, that in all instances the military work closely with other Government Departments and non-governmental organisations to agree key priorities with the Afghan authorities. In many instances, project delivery will require the involvement of a number of agencies. This is in line with our comprehensive approach.

In addition to the projects in the following table, there are a number of long-term development initiatives being undertaken throughout Afghanistan, to which the Department for International Development (DFID) contributes. DFID funds around $60 million over three years (2006-09) in support of their Helmand Agriculture and Rural Development Programme.

Security

Responsible agency

Agency responsible to MOD

Location

Title

Total cost ($)

Status

Royal Engineers

Yes

Lashkar Gah

Permanent Vehicle Check Point (PVCP)

21,387

Complete

Royal Engineers

Yes

Gereshk

Afghan National Police (ANP) Infrastructure in Gereshk

240,000

Complete

Royal Engineers

Yes

Lashkar Gah

Afghan National Army (ANA) Platoon House

40,387

Complete

Royal Engineers

Yes

Lashkar Gah

ANP Outposts

143,964

Complete

Royal Engineers

Yes

Lashkar Gah

4 x PVCPs

155,000

Complete

Royal Engineers

Yes

Lashkar Gah

4 x Enhanced PVCPs

110,000

Complete

Royal Engineers

Yes

Helmand

Construction resources for 12 modular Military Construction Force built ANP temporary police stations/PVCPs

600,000

Complete

Royal Engineers

Yes

Lashkar Gah

New Joint Provincial Coordination Centre

161,147

Complete

Governor’s Office

No

Lashkar Gah

2 x PVCPs

16,800

Complete

Royal Engineers

Yes

Lashkar Gah

Ablutions at US Protection and Investigations (USPI) compound for Afghan National Auxiliary Police (ANAP) training

5,265

Complete

Royal Engineers

Yes

Tombstone

Camp Shorabak (ANA) Mosque

100,000

Planned

Royal Engineers

Yes

Lashkar Gah

Provision of security infrastructure for Governor’s office and Bost Hotel

84,227

In progress

Operational Mentoring and Liaison Team (OMLT)

Yes

Kajaki

Water/Fuel storage for the ANA

1,200

In progress

Royal Engineers

Yes

Gereshk

Upgrade to ANA compound in Gereshk

15,000

Complete

Operations Company

Yes

Laskhar Gah

Upgrade to Muktar Gate

6,475

In progress

42 Commando

Yes

Nowzad

Rubble Clearance

0

In progress

Royal Military Police (RMP)

Yes

Lashkar Gah

Bonus Scheme for ANP top-performers at PVCPs

3,000

In progress

Information Exploitation Group

Yes

Garmsir

Garmsir PVCP repairs

700

In progress

Provincial Reconstruction Team (PRT)

No

Lashkar Gah

Afghan Meeting facility

651

Complete

Total

1,705,203

Social and economic development

Responsible agency

Agency responsible to MOD

Location

Title

Total cost ($)

Status

Helping Afghan Farmers Organisation (HAFO)

No

Gereshk

Sayed Tajdar Shrine: wall and gate construction

21,224

Complete

HAFO

No

Gereshk

Sayed Tajdar Shrine: road and footpath construction

33,076

Complete

HAFO

No

Lashkar Gah

Improvement of Friday market and Gabion wall

140,623

Complete

HAFO

No

Cha-i-Anjeer

Improvement of Friday market

24,950

Complete

HAFO

No

Lashkar Gah

Gabion Extension

34,108

Complete

Royal Engineers

Yes

Lashkar Gah

Safean Playground

50,000

In progress

PRT

No

Lashkar Gah

Support to Office of Governor to respond to Internally Displaced Persons (IDPs) needs

60,000

Complete

Information Operations (IO)

Yes

Lashkar Gah

improvements to Media Centre

8,336

Complete

Civil-Military Co-operation (CIMIC)

Yes

Lashkar Gah/Gereshk

Installation of solar-powered lighting

280,960

In progress

IO

Yes

Lashkar Gah

Support to Radio Stations

150,000

In progress

HAFO

No

Lashkar Gah

Weir on Helmand River

161,848

Complete

HAFO

No

Lashkar Gah

Extension of Gabion walls on Helmand River

168,045

Complete

HAFO

No

Lashkar Gah

Silt Removal from Helmand River

259,479

Complete

Royal Engineers

Yes

Lashkar Gah

Bost Hospital Generator and Mortuary

130,400

Complete

Royal Engineers

Yes

Lashkar Gah

Security wall for Women’s Centre

30,000

Complete

Royal Engineers

Yes

Lashkar Gah

Building work for Kartelegan and Toortank day care centres

86,052

Complete

CIMIC

Yes

Lashkar Gah

Women’s Centre sewing ISAF badges to UK mil uniforms

750

Complete

Governor’s Office

No

Nahrisiraj

Work to clear and strengthen stretch of Nahrisiraj canal

12,000

Complete

Royal Engineers

Yes

Lashkar Gah

Construction of 8 new classrooms at Zacor School

80,008

In progress

Royal Engineers

Yes

Lashkar Gah

Connection of a new school to electricity grid

1,809

Complete

Royal Engineers

Yes

Lashkar Gah

Construction of a 20 room midwifery hostel

221,762

In progress

Royal Engineers

Yes

Lashkar Gah

Construction of a perimeter wall for Cha I Anjeer school

25,000

Complete

Royal Engineers

Yes

Lashkar Gah

Essential repairs to Bolan Bridge

231,728

In progress

CIMIC

Yes

Lashkar Gah

Welfare Association for Development of Afghanistan (WADAN) Playground

1,090

Complete

Royal Engineers

Yes

Lashkar Gah

Repairs to 3 schools

185,062

In progress

Royal Engineers

Yes

Lashkar Gah

Improvements to Lashkar Gah library

13,925

Complete

CIMIC

Yes

Lashkar Gah

Sports equipment for 8 schools

0

Planned

CIMIC

Yes

Lashkar Gah

School sports equipment

30,000

Planned

Royal Engineers

Yes

Lashkar Gah

Kartelegan Playground

52,237

Complete

CIMIC

Yes

Lashkar Gah

Welfare Centre Kitchen

15,819

In progress

HAFO

No

Lashkar Gah

Women’s Park

840,813

In progress

Royal Engineers

Yes

Lashkar Gah

New School in Qala-e-Khana

0

Complete

Royal Engineers

Yes

Lashkar Gah

Refurbishment of Nawa School

72,713

In progress

Ministry of Public Health

No

Lashkar Gah

Rapid Assessment of Mukhtar IDP camp

973

Complete

Royal Engineers

Yes

Musa Qaleh

Repairs to 3 mosques

350,000

Planned

Royal Engineers

Yes

Gereshk

Playground and Football pitch

39,098

In progress

Royal Engineers

Yes

Gereshk

Seminar Awal School repairs

0

Planned

Royal Engineers

Yes

Gereshk

Technical School repairs

0

Planned

Royal Engineers

Yes

Gereshk

Abolfathi Botsi Boys School Repairs

0

Planned

CIMIC

Yes

Lashkar Gah

Ministry of Agriculture Tree

6,750

In progress

Royal Engineers

Yes

Garmsir

Reconstruction using local labour—road, wells, ditches

4,000

In progress

Royal Engineers

Yes

Garmsir

Culvert bridge

500

In progress

Royal Engineers

Yes

Garmsir

Bore Hole and Hand Pump

1,750

In Progress

Royal Engineers

Yes

Nahr-e-Saraj

Lashkar Gah-Gereshk canal road culvert and gravel track repairs

28,272

In progress

Royal Engineers

Yes

Lashkar Gah

3 km asphalt road and solid drainage Kartelegan-601

429,950

In progress

CIMIC

Yes

Garmsir

CHC Generator Repair

505

In progress

CIMIC

Yes

Lashkar Gah/Gereshk

Midwifery Kits

5,416

In progress

Stabilisation Advisor (STABAD)

No

Lashkar Gah

Carpet weaving pilot project

82,733

In Progress

CIMIC

Yes

Lashkar Gah

Furniture for Zacor High School

20,000

Complete

PRT

No

Helmand

Support to Director of Rural Rehabilitation and Development (DRRD) for Musa Qaleh IDPs

800

Complete

CIMIC

Yes

Gereshk

Refuse Collection Points and new trucks

34,000

In progress

CIMIC

Yes

Lashkar Gah

Upgrade to Bost Hospital Grounds

150,860

In progress

CIMIC

Yes

Gereshk

Furniture for Gereshk Women’s Group

1,920

Complete

HAFO

No

Lashkar Gah

Lashkar Gah Bus Station

854,327

In progress

UK Task Force (UKTF)

Yes

Garmsir

Wells and Water Tower

10,800

In progress

Royal Engineers

Yes

Lashkar Gah

Covered waiting area at Bost Hospital

7,000

Complete

Royal Engineers

Yes

Lashkar Gah

Reconstruct Dept of Land Registry

98,142

In progress

CIMIC

Yes

Helmand

Procure 3 GPS units

500

In progress

PRT

No

Helmand

Provide Plant Machinery to DRRD

2,268,000

In progress

Police Mentors

No

Lashkar Gah

Additional Support to the Traffic Division

40,000

In progress

Total

7,860,113

Governance

Responsible agency

Agency responsible to MOD

Location

Title

Total cost ($)

Status

BBC World Service (BBCWS)

No

Lashkar Gah/Gereshk

Radio Transmitter

94,231

Complete

RMP

Yes

Helmand

ID card making facility (ANP)

30,295

Complete

PRT

No

Lashkar Gah

Generators for the Governor’s Office and compound

220,186

Complete

Justice Advisor

No

Lashkar Gah

Wall for the Office of the Prosecutor

10,000

Planned

Governance Advisor

No

Lashkar Gah

Refurbish of Offices for Provincial Government Departments

32,000

In progress

IO

Yes

Lashkar Gah

Rehabilitate Printing Press

224,098

In progress

Governor’s Office

No

Musa Qaleh

Set up costs for Musa Qaleh District Administration

10,000

Complete

RMP

Yes

Lashkar Gah

Equipment for 8 PVCPs

32,584

In progress

PRT

No

Lashkar Gah

Additional support to the Dept of Hajj

24,167

In progress

Police Mentors

No

Lashkar Gah

Support to ANP Traffic Division

32,631

In progress

Total

710,192

Counter-narcotics (CN)

Responsible agency

Agency responsible to MOD

Location

Title

Total cost ($)

Status

Royal Engineers

Yes

Lashkar Gah

Regrading of Bost Airfield

555,000

In progress

MNCC

No

Lashkar Gah

Windmill Wells

10,640

In progress

Royal Engineers

Yes

Lashkar Gah

Upgrade to Lashkar Gah prison

45,385

Complete

British Embassy Drugs Team (BEDT)

No

Lashkar Gah

Comms equipment for the Counter-Narcotics Police Authority (CNPA)

8,900

Complete

BEDT

No

Helmand

PA Systems for 12 District Centres

3,000

Complete

BEDT

No

Helmand

CN Tractor Repairs

12,000

Complete

BEDT

No

Helmand

CN Tractor Ploughs

30,000

Complete

BEDT

No

Lashkar Gah

Tractors and equipment for the Governor

884,718

In progress

Royal Engineers

Yes

Lashkar Gah

Repair to bomb-damage at the Directorate of Counter-Narcotics

21,079

Complete

BEDT

No

Lashkar Gah

Upgrade to Counter Narcotics Provincial Administration

88,925

In progress

BEDT

No

Lashkar Gah

Incinerator for Bost hospital

30,000

In progress

BEDT

No

Lashkar Gah

Uniforms for the Prison Staff

5,000

Complete

BEDT

No

Lashkar Gah

Computer for Chief of Police

1,761

Complete

BEDT

No

Lashkar Gah

Support to the Counter Narcotics Provincial Administration

340,000

In progress

Total

2,031,408

To ask the Secretary of State for Defence (1) which British military units are deployed to Afghanistan, broken down by Afghan province; (135362)

(2) when he plans to update the list of units deployed to Afghanistan on his Department’s website.

[holding answer 2 May 2007]: Following the recent roulement of forces in Afghanistan, an up to date list of military units deployed to Afghanistan is now available on the MOD website.

http://www.mod.uk/DefenceInternet/FactSheets/Operations Factsheets/OperationsInAfghanistanBritishForces.htm

To ask the Secretary of State for Defence how many (a) British and (b) Afghan (i) armed forces members and (ii) civilians were killed in (A) each of the years since the present conflict began and (B) in each month of the most recent year. (135785)

[holding answer 8 May 2007]: The numbers of UK military and civilian personnel killed or injured in Afghanistan are published on the Ministry of Defence website:

http://www.mod.uk/DefenceInternet/FactSheets/Operations Factsheets

and are in the following tables. Figures cover military personnel and UK civilians employed, or contracted, by the MOD.

Number of UK military and civilian fatalities from 7 October 2001 to 31 December 2006

Number

2001

0

2002

3

2003

0

2004

1

2005

1

2006

39

Number of UK military and civilian fatalities in 2007 by completed month

Number

January

2

February

2

March

4

April

1

Figures for Afghan armed forces fatalities are not held by the UK and are a matter for the Afghan National Government. There are no reliable means of ascertaining the numbers of Afghan civilians killed during the period since the conflict began. The UK makes every effort to minimise the impact of military action on the Afghan population.