To ask the Secretary of State for Communities and Local Government what the average time taken by (a) Warrington borough council and (b) councils in (i) the north-west and (ii) England is to determine an application for (A) council tax benefit and (B) planning permission. (142459)

[holding answer 12 June 2007]: The average time taken by Warrington borough council and councils in the north-west and England to determine an application for council tax benefit is set out in the following table:

Council tax benefit claims

Average days taken in 2006-071

Warrington

27

North-west

36

England

34

1 April to December 2006

Source:

Department for Works and Pensions

Information on the average time taken to determine planning permission is not collated centrally. However, the number of applications decided in 2006-071 is set out in the following table:

Planning permission

Percentage

Up to 8 weeks

Up to 13 weeks

More than 13 weeks

Warrington

91

98

2

North West

84

94

6

England

82

93

7

1 April to December 2006

Source: