Skip to main content

M1

Volume 461: debated on Thursday 21 June 2007

To ask the Secretary of State for Transport when the carriageways of the M1 motorway between junctions 26 and 27 are next scheduled to be resurfaced. (144139)

The M1 motorway between junctions 26 and 27 forms part of the M1 J21—J30 widening contract 1. As part of this widening programme, all the carriageways will be re-surfaced providing a new low noise surface. Subject to the satisfactory completion of statutory procedures and approved funding, Contract 1 work is planned to start in late 2007.