To ask the Secretary of State for Business, Enterprise and Regulatory Reform what is the estimated cost of extending the life of Wylfa power station for nine months beyond its planned closure date; and if he will make a statement. (167010)

The Nuclear Decommissioning Authority (NDA) has asked Magnox Electric Ltd to prepare a business case for extending the life of Wylfa power station by nine months beyond its planned closure date for consideration in early 2009. The business case will include a robust estimate of the costs of an extension. An initial study in November 2005 estimated that the cost of an extension would be some £110 million.