There are a large number of information technology projects across the Northern Ireland Office. The majority of these are relatively small and are developed in-house with minimum cost. To compile information to support all projects would be at disproportionate cost therefore the information within the following table relates only to current IT projects which cost in excess of £l million.
Causeway PRISM Access NI Start date August 2003 March 2002 June 2006 Original planned completion date December 2006 December 2005 March 2007 Expected completion date December 2009 March 20081 March 2008 Originally planned costs (£ million) 45 5.12 l.84 Estimated planned costs (£ million) 61 5.97 l.3 1 Implementation commenced in the first prison establishment on September 2005. Implementation is planned to be completed in all prison establishments by March 2008.