My Department is undertaking the following information technology projects:
Project (a) Start date (b) Original planned completion date (c) Current expected completion date (d) Planned cost (e) Current estimated cost Electronic document management system October2007 October 2008 October 2008 £1.5 million £1.5 million Migration of Department's websites to new content management system February2008 June 2008 June 2008 £250,000 £250,000 Migration of ICT services to a new outsourcing contract January 2008 May 2008 May 2008 £647,000 £647,000