The Regional Control Centre (RCC) building leases commence five working days after practical completion of the buildings. Four buildings have achieved practical completion, as detailed in Table 1.
Region Practical Completion Date Building Lease Began Lease Term (years) East Midlands 29 June 2007 6 July 2007 25 North East 29 June2007 6 July 2007 20 South West 15 August 2007 22 August 2007 20 West Midlands 20 December 2007 27 December 2007 25
The remaining five RCC buildings are contracted to achieve practical completion as detailed in Table 2.
Region Practical Completion Date Building Lease Begins Lease Term (years) South East 14 May 2008 21 May 2008 25 North West 1 July 2008 8 July 2008 25 Yorkshire and Humberside 1 July 2008 8 July 2008 20 East of England 1 October 2008 8 October 2008 25 London 26 February 2010 5 March 2010 25