Skip to main content

Fire Services: Buildings

Volume 472: debated on Wednesday 20 February 2008

To ask the Secretary of State for Communities and Local Government when the lease for each of the proposed regional control centres in respect of the FiReControl Project commences; how long each lasts; and if she will make a statement. (186134)

The Regional Control Centre (RCC) building leases commence five working days after practical completion of the buildings. Four buildings have achieved practical completion, as detailed in Table 1.

Table 1: RCC buildings that have achieved practical completion

Region

Practical Completion Date

Building Lease Began

Lease Term (years)

East Midlands

29 June 2007

6 July 2007

25

North East

29 June2007

6 July 2007

20

South West

15 August 2007

22 August 2007

20

West Midlands

20 December 2007

27 December 2007

25

The remaining five RCC buildings are contracted to achieve practical completion as detailed in Table 2.

Table 2: Planned dates for remaining RCC buildings

Region

Practical Completion Date

Building Lease Begins

Lease Term (years)

South East

14 May 2008

21 May 2008

25

North West

1 July 2008

8 July 2008

25

Yorkshire and Humberside

1 July 2008

8 July 2008

20

East of England

1 October 2008

8 October 2008

25

London

26 February 2010

5 March 2010

25