Departmental ICT

Volume 472: debated on Wednesday 27 February 2008

To ask the Secretary of State for Business, Enterprise and Regulatory Reform what the (a) start date, (b) original planned completion date, (c) current expected completion date, (d) planned cost and (e) current estimated cost is for each information technology project being undertaken by his Department and its agencies; and if he will make a statement. (180563)

The information is as follows:

Project

Start date

Original completion

Expected completion

Planned cost (£)

Expected cost (£)

e-HR

July 2006

Q1 2008

Under review

5.2 million

Under review

HR Intranet

August 2006

February 2008

May 2008

160,000

160,000

Infrastructure (portfolio)

Ongoing upgrade activities

Ongoing upgrade activities

Ongoing upgrade activities

1750,000

1750,000

Point of single contact

December 2007

Qtr 2 2009

Qtr 2 2009

2.5 million

2.5 million

Web improvement

January 2008

Qtr 3 2008

Qtr 3 2008

800,000

800,000

1 Per annum

Notes:

1. The draft answer refers to the core BERR Department only. The agencies will provide their own responses.

2. The increased costs of e-HR relate to:

(a) Increases in scope;

(b) Implementation delays through MOG changes and gaining agreement on configuration and customisation. The system will be used by core BERR, INSS, UKIPO and NWML.

Letter from Gareth Jones, dated 27 February 2008:

I am responding on behalf of Companies House to your recently tabled Parliamentary Question to the Secretary of State for Business Enterprise and Regulatory Reform.

Please find in the attached appendix the details you requested regarding IT projects currently being undertaken within Companies House.

The CHIPS programme is a highly complex bespoke development, which has been custom designed and built, to replace the existing bespoke application that supports the Companies Register.

The project, initially contracted out, was brought in house in February 2004. The original planned completion date for the in-house development was August 2006, but this date changed subsequently and I have detailed revised plans for your information.

Impairment reviews in the last two financial years have led to a write down in value of £12.1m. This represents the value of all contractual work undertaken on behalf of Companies House on the project prior to February 2005.

Project

Start Date

Original planned completion date

Current expected completion date

Original planned cost

Current estimated cost

CHIPS

Project contract

April 2001

April 2005

29 million

Project brought in house

January 2004

August 2006

30 million

Plan revision

February 2005

November 2006

41 million

Plan revision

January 2007

October 2007

February 2008

48 million

51 million

CAP programme

December 2005

October 2008

October 2009

15 million

15 million

Bilingual Welsh filing project

June 2007

August 2007

June 2008

61,000

61,000

IT service continuity project

March 2006

January 2007

1June 2008

785,000

785,000

WEB Systems capacity upgrade

July 2006

October 2006

February 2008

149,000

149,000

XML Conversion—STAR

July 2006

April 2008

July 2008

119,000

119,000

Government Gateway—STAR

March 2007

May 2008

October 2009

223,000

223,000

1 Completion on hold until CHIPS live

Letter from Stephen Speed, dated 27 February 2008:

The Secretary of State for Business, Enterprise and Regulatory Reform has asked me to reply to your question (2007/1098) asking what the (a) start date, (b) original planned completion date, (c) current expected completion date, (d) planned cost and (e) current estimated cost is for each information technology project being undertaken by his Department and its agencies; and if he will make a statement.

Project

Start date

Original planned completion date

Current expected completion date

Planned cost (£000)

Current estimated completion cost (£000)

Technology Refresh, five year Managed Service

June 2007

June 2008

July 2008

23,510

23,810

Functional Support Services Document Production

August 2007

March 2008

April 2009 (scope extended)

12,030

22,030

Time Recording

August 2007

March 2008

July 2009 (scope extended)

1

2

(ICM) Electronic Document Management and scanning

August 2006

March 2009

March 2009

2,400

3,979

(CHAMP) Claims Handling and Making Payments

July 2005

September 2008

October 2008

1,930

2,451

Debt Relief Orders

October 2006

April 2009

April 2009

1,389

1,392

Corporate Reporting and Data Migration

June 2006

September 2010

August 2009

1,460

1,445

Estate Accounting System

August 2008

May 2010

December 2008

7,300

7,300

(ISCIS) Insolvency Service Case Information System (Current Initiation)

July 2006

March 2008

October 2008

6,650

8,120

Company Investigations Case Management System

October 2007

July 2008

July 2008

396

396