M69: Repairs and Maintenance

Volume 475: debated on Tuesday 13 May 2008

To ask the Secretary of State for Transport when she expects the roadworks taking place on the M69 to be completed and all carriageways re-opened to traffic. (204743)

The resurfacing work on the M69 is due to be completed and all carriageways re-opened by the end of the second week in May.

To ask the Secretary of State for Transport for what reasons the roadworks taking place on the M69 were carried out concurrently to the roadworks taking place on the M1 motorway near junction 26; and if she will make a statement. (204744)

The work currently being undertaken on the M1 near Junction 26 is part of an ongoing major widening scheme; the M69 work is a shorter scale resurfacing scheme. To minimise disruption to road users, the Highways Agency’s policy is to ensure, where possible, that concurrent roadworks are not carried out within 10 km of each other. The M1 and M69 schemes comply with that policy, being more than 50 kms apart.