Skip to main content

Building Schools for the Future Programme

Volume 480: debated on Wednesday 8 October 2008

To ask the Secretary of State for Children, Schools and Families what the (a) original expected completion date and (b) current expected completion date is of each Building Schools for the Future project; and what the reasons are for delays in completion of projects in each case where there is a delay. (223734)

Building Schools for the Future is the most ambitious school building programme for a generation. As you would expect of a programme of this scale, there have been challenges and lessons have been learned from the early projects. These have led to improvements in the process supporting the delivery of BSF and in local authority preparations for joining the programme. The key reasons for the delays in some of the early local authority projects are as follows:

many local authorities in the early waves of the programme found identifying and resourcing the necessary project management skill sets to deliver the programme more challenging than expected;

a focus on “getting it right” to ensure that strategies are educationally transformational rather than simply focusing on pace of delivery has led to some authorities taking longer than originally expected to develop their education and procurement strategies; and

in the early waves the selected local authorities had the biggest challenges to manage, were pioneering the processes, and were at the forefront of resolving unexpected difficulties with innovative solutions.

The following table provides a comparison between the original expected project completion date and the current expected date for each local authority in the first three waves of BSF. Where specific local issues have impacted on the delivery timetable, these are also described.

Local authority

Original expected project completion date

Current expected project completion date

Major reasons for delay

Wave 1

Bradford

December 2007

September 2008

Challenging original completion expectations; Issues around use of untested processes

Bristol

April 2008

January 2009

Challenging original completion expectations; Issues around use of untested processes

Greenwich

April 2009

September 2011

Piloting of non-standard BSF procurement model by local authority has been problematic and has caused considerable delay; Local resourcing difficulties; Issues around use of untested processes

Knowsley

September 2009

January 2010

Issues around use of untested processes

Lancashire

September 2010

August 2010

Leeds

September 2010

September 2011

Issues around use of untested processes

Leicester

September 2011

September 2011

Lewisham

July 2010

September 2010

Issues around use of untested processes

Manchester

September 2009

June 2011

Challenging original completion expectations; Issues around use of untested processes; later project rescoping, including integrating seven new academies

Newcastle

March 2011

March 2011

Newham

January 2009

March 2011

Challenging original completion expectations; Issues around use of untested processes; Local resourcing difficulties

Sheffield

March 2010

April 2011

Challenging original completion expectations; Issues around use of untested processes

Solihull

September 2008

September 2009

Challenging original completion expectations; Issues around use of untested processes

STaG

December 2012

January 2013

Issues around use of untested processes

Sunderland

Jan 2010

September 2010

Challenging original completion expectations; Issues around use of untested processes

Waltham Forest

September 2008

September 2008

Wave 2

Birmingham

September 2010

September 2011

Challenging original completion expectations; Local resourcing difficulties; More time taken to develop transformational strategy; later project rescoping, including integrating new academies

Hackney

September 2013

November 2013

Issues around use of untested processes

Haringey

March 2011

October 2011

Issues around use of untested processes

Islington

September 2011

September 2012

Local resourcing difficulties; More time taken to develop transformational strategy

Kingston-upon-Hull

September 2014

September 2014

Lambeth

September 2010

September 2010

Liverpool

September 2010

September 2011

Local resourcing difficulties; More time taken to develop transformational strategy; Issues around use of untested processes; Piloting of non-standard BSF procurement model by local authority has caused some delay

Middlesbrough

September 2011

September 2012

Local resourcing difficulties; changes to procurement strategy to achieve a better value for money outcome caused some delay

Nottingham

December 2010

December 2010

Tower Hamlets

June 2011

December 2011

Local resourcing difficulties; More time taken to develop transformational strategy

Wave 3

Barnsley

September 2011

September 2011

Bradford

August 2010

August 2010

Derbyshire

August 2011

August 2011

Durham

September 2011

September 2011

Kent

April 2011

July 2011

Luton

September 2010

November 2012

Local resourcing difficulties; Issues around identifying new sites for new schools have caused delay to the project

N Lincs

June 2011

April 2012

Local resourcing difficulties; More time taken to develop transformational strategy

Salford

January 2012

September 2012

More time taken to develop transformational strategy

Sandwell

March 2011

July 2011

More time taken to develop transformational strategy

Southwark

November 2014

April 2014

Tameside

January 2011

February 2011

More time taken to develop transformational strategy

Westminster

December 2010

November 2010

Notes:

1. Formal baseline dates were only set for the first wave. Expected completion dates for projects beyond wave 3 are not confirmed until the outline business case is approved.

2. Stoke, a Wave 1 project, is currently reviewing the proposals and timelines put forward in its outline business case following the Children’s Services going into intervention and therefore has not been included as the expected finish date has not been finalised.