The IT projects currently being undertaken by Communities and Local Government and its agencies are as follows:
Project Expected completion date Estimated costs (£000) Website Rationalisation (incorporating Interlocal Rebuild project)1 December 2008 3,600 Fire Incident Recording System November 2008 3,040 Data Interchange Hub Release 2 March 2009 1,273 EDRMS November 2008 754 SAP Implementing Benefits February 2009 364 Smarter Business Process (SAP Enhancement) November 2008 362 Business Intelligence System Technical Upgrade February 2009 351 PIMS HR e-Strategy Implementation October 2008 287 Government Offices National Indicator Analysis tool—scoping December 2008 62 Government Offices Human Resources Database—Phase 2 March 2009 241 Government Offices Online Performance Management System -Phase 2 March 2009 82 Government Offices Contacts Database March 2009 40
Agencies of the Department
Project Expected completion date Estimated costs (£000) Fast Track Householder Appeals—Stage 2 (Implementation) May 2009 175 Business Continuity Planning (BCP) and January 2009 and 2142 Disaster Recovery (DR) June 2009 2— Charging for Appeals April 2009 100
Project Expected completion date Estimated costs (£'000) Meeting Matrix October 2008 65
1 A project to rebuild the Info41ocal website was approved in November 2004 at a cost of £244,000. The project was deferred for later incorporation into the Department’s Website Rationalisation Project at a final cost of £400,000 on top of the £3,600,000 included above for web rationalisation.
Note:
Estimated costs are the build costs only.