All the national programme for information technology local service provider (LSP), and national application service provider (NASP), contracts include provisions appropriate to contracts of their size and complexity to address foreseeable development, delivery and service issues, including terms that permit the issue of a breach of contract notification under defined conditions.
In the case of the Fujitsu LSP contract, 41 breach of contract notices were issued, which ultimately resulted in the termination of the contract on 28 May 2008.
None of the remaining LSP and NASP providers, including BT, have been issued with formal breach of contract notices. However, as part of the normal contractual processes, a number of so-called ‘contractor event of default’ notices have been issued, reflecting operational matters identified during the normal course of contract delivery that need to be addressed. All the matters identified have been addressed using the existing contractual remedies.
Information requested on deployments, through the national programme for information technology, of the Cerner Millennium system in acute national health service trusts is in the following table.
Acute trust Software version Technical go-live (TGL)1 Winchester and Eastleigh Healthcare NHS trust RO 9 February 2007 Surrey and Sussex Healthcare NHS trust RO 19 April 2007 Weston Area Health NHS trust RO 29 July 2006 Taunton and Somerset NHS Foundation trust RO 14 December 2007 Nuffield Orthopaedic Centre NHS trust RO 20 December 2005 Milton Keynes General Hospital NHS trust RO 23 February 2007 Buckinghamshire Hospitals NHS trust RO 25 September 2006 Worthing and Southlands Hospitals NHS trust RO 28 September 2007 Barnet and Chase Farm Hospitals NHS Trust RO 21 July 2007 Queen Mary’s Sidcup NHS Trust RO 28 October 2007 Barts and The London NHS trust RO 6 April 2008 Royal Free Hampstead NHS trust LC1 15 June 2008 1 TGL refers to when the system was first technically enabled and available for use, prior to ‘business go-live’ (BGL), when systems begin to be used for live transactions. There may be a delay between TGL and BGL, for example to allow time for users to be trained or to allow other dependent deployments to proceed. Note: Comprehensive information of the kind requested about the financial and resource impact, if any, resulting from implementation of the Cerner system is not held centrally, and could be obtained only at disproportionate cost.