The running costs for the eight regional control centres (RCCs) which have completed their commissioning process—‘practical completion’—are shown for October, broken down by region, in the following table:
Region Running costs (£) NE 143,994 EM 145,889 SW 140,839 WM 113,463 SE 46,142 NW 36,920 Y and H 48,558 EoE 84,617
These eight buildings are in the process of being fitted out, including installing the IT hardware, AV screens and furniture. Note, the range reflects the relative stages of completion. Therefore, no regional control centre is yet operational.
In the interim the buildings are used for a range of purposes including Fire and Rescue Service meetings and workshops to progress FiReControl work. In many cases the regional project team works out of the RCC.
Under Fire Control, the risk management toolkit will replace the fire service emergency cover toolkit and will be rolled out prior to the point at which there is an FRS cut-over.