From 2004 to 2008 the Environment Agency’s National Capital Programme Management Service (NCPMS) was responsible for a total of 146 completed projects. Of these, 83 were completed early or on time and 63 were completed after the expected date. Information prior to 2004 is not available as records were not held centrally.
Details of the projects have been placed in the Libraries of the House.
Since the floods in July 2007 49 projects have been completed by the Environment Agency and 143 projects are under instruction. This includes many places which were flooded in the summer of 2007.
We have already taken a number of steps in response to Sir Michael Pitt’s findings and will be publishing a detailed response setting out implementation to date and further actions shortly.
The Government’s detailed response to the Pitt review will be published shortly.