To ask the Secretary of State for Transport what investigations the Highways Agency has undertaken into the state of the culvert under the A435 in Ashchurch parish; and if he will make a statement. (251920)

The A435 through Ashchurch has now been renumbered the A46. The culvert has been the subject of CCTV investigation to identify its condition. Debris which had collected at the southern outfall of the culvert has been cleared and the location is regularly monitored and clearance work undertaken as appropriate. The CCTV survey has shown that there is a problem with disjointed pipework and blockages within the culvert and a scheme is currently being costed by the Highways Agency and will be added to a future works programme.