To ask the Minister for the Olympics what her assessment is of the extent to which Aggregate Industries Ltd is meeting the contractually stipulated target of delivering 99 per cent. of aggregate materials to the Olympic Park by sustainable means. (250419)

[holding answer 27 January 2009]: The Olympic Delivery Authority's target that at least 50 per cent. of all materials, by weight, be transported to the Olympic Park by non-road methods is being exceeded. Aggregate Industries Ltd is currently achieving a performance level of 84 per cent. against that target.

Aggregate Industries' own target is that 99 per cent. of materials be transported by non-road methods.