To ask the Secretary of State for Environment, Food and Rural Affairs what estimate he has made of the sum required to clear the maintenance backlog experienced by British Waterways; and if he will make a statement. (256164)

The KPMG report commissioned by British Waterways concluded that there is a significant gap between current expenditure and that required under steady state to maintain its waterways. However, British Waterways have advised that current expenditure is sufficient to maintain the network in a reasonable and safe condition for this comprehensive spending review (CSR) period. In this context, there is no safety backlog though British Waterways estimates that it would cost around £200 million to bring all principal and non principal assets up to steady state condition.