Warm Front Scheme

Volume 490: debated on Friday 27 March 2009

To ask the Secretary of State for Energy and Climate Change how many Warm Front installations took (a) more than 30, (b) more than 60, (c) more than 90, (d) more than 120, (e) more than 150 and (f) more than 180 working days from survey to completion of the work in each of the last five years. (257474)

Warm Front installation timescales are not recorded in the periods requested. They are recorded against the timescales put in place by the Department at the inception of the Scheme.

These timescales are detailed in the table, which provides information from the inception of the current phase of Warm Front in 2005.

Warm Front Installations

Percentage

2005-06

2006-07

2007-08

2008-09

Heating(Time Band)

Within 120 days (%)

92

80

89

90

Outside 120 days (%)

8

20

11

10

Insulation (Time Band)

Within 40 days (%)

79

75

82

72

Outside 40 days (%)

21

25

18

28