Warm Front installation timescales are not recorded in the periods requested. They are recorded against the timescales put in place by the Department at the inception of the Scheme.
These timescales are detailed in the table, which provides information from the inception of the current phase of Warm Front in 2005.
Percentage 2005-06 2006-07 2007-08 2008-09 Heating(Time Band) Within 120 days (%) 92 80 89 90 Outside 120 days (%) 8 20 11 10 Insulation (Time Band) Within 40 days (%) 79 75 82 72 Outside 40 days (%) 21 25 18 28