M25: Repairs and Maintenance

Volume 491: debated on Tuesday 21 April 2009

To ask the Secretary of State for Transport what his Department's timetable is for work to widen stretches of the M25. (268991)

The widening of the M25 between Junctions 16 to 23, and Junctions 27 to 30, is included in the scope of the M25 Design, Build Finance and Operate (DBFO) Contract, currently in the final stages of procurement. Subject to satisfactory completion of statutory processes and completion of the ongoing competition to secure finance for the project, the widening works are planned to take place as follows:

Start

Complete

Junctions 16 to 23

27 April 2009

July 2012

Junctions 27 to 30

20 July 2009

July 2012

Two further sections of the M25 are being considered by the Highways Agency as part of the Managed Motorways programme, where hard shoulder running is envisaged rather than widening.

The earliest dates for construction of these two sections are:

Start

Complete

Junctions 5 to 7

late 2012

late 2013

Junctions 23 to 27

late 2012

late 2013