There has been notable progress made in delivering the FiReControl project by all delivery partners at the local, regional and national level. These include:
fire and rescue authorities in each region coming together to establish local authority controlled companies to run the Regional Control Centres;
eight out of nine highly resilient Regional Control Centre buildings built, with London on track for completion in February 2010; and
a full programme to survey all Fire Stations to enable New Station End equipment is under way and to date 558 out of 1,410 have been completed.