Construction at the St. Athan site is expected to begin shortly after contract award for the Defence Training College, which is anticipated to be signed in the summer of 2010. However, some site clearance and demolition work is expected to take place to prepare the site before contract signature. The construction of the Defence Training College is expected to be completed by 2014.
Estimated construction costs for the first five years of the contract are provided in the following table.
Cost (£ million) 2010-11 112.5 2011-12 200.7 2012-13 265 2013-14 156.1 2014-15 37.8