Of the 27 recommendations in the report, 23 have been implemented. It is anticipated that, of the four remaining recommendations, two covering design drawings and maintenance of underground pipe work will be completed by the end of September 2009.
It has been decided that the final two recommendations, which cover the requirement for safety justification and for new equipment, can best be addressed as part of a future options study to determine Her Majesty’s Naval Base Clyde’s long-term plans for radioactive waste management arrangements. This is due to report in the first quarter of 2010.
In the meantime, all radioactive waste handling is carried out in accordance with procedures that have been agreed with the appropriate regulatory bodies, including the Scottish Environment Protection Agency.