To ask the Minister of State, Department for Business, Innovation and Skills how much each regional development agency spent on land reclamation projects in each year since 2000; and if he will make a statement. (265242)

The following table shows RDAs expenditure on land reclamation projects in each year since 2000. Figures are not yet available for 2008-09.

The figures provided include funds allocated to the ‘Land Reclamation Programmes’ inherited by RDAs from English Partnerships and, following their conclusion, any new environmental improvement programmes which have succeeded them.

£ million

RDA

2000-01

2001-02

2002-03

2003-04

2004-05

2005-06

2006-07

2007-08

AWM

40

50

44

102

80

56

59

46

EEDA

1

13

21

24

37

25

11

EMDA

5

13

13

3

7

2

4

5

LDA

103

149

140

108

129

122

131

144

NWDA

20

23

20

18

15

6

17

39

ONE

22

20

14

3

2

5

2

0.6

SEEDA

6

1

21

11

40

17

11

5

SWRDA

1

1

32

21

17

27

22

32

YF

12

5

6

4

1

0.5

0.7

0.2

1 Due to a change in management recording system during 2002-03, producing figures before 2002-03 would incur disproportionate cost.

To ask the Minister of State, Department for Business, Innovation and Skills how many land reclamation projects regional development agencies (a) started and (b) completed in each year since 2000. (265278)

The following tables shows land reclamation projects started and completed by RDAs in each year since 2000 to 2008. Figures are not yet available for 2008-2009.

The figures provided include funds allocated to the ‘Land Reclamation programmes’ inherited by RDAs from English Partnerships and, following their conclusion, any new environmental improvement programmes which have succeeded them.

Projects started

RDA

2000-01

2001-02

2002-03

2003-04

2004-05

2005-06

2006-07

2007-08

AWM

6

9

37

8

5

4

8

4

EEDA

5

2

16

15

4

8

13

2

EMDA

30

71

28

9

4

5

15

42

LDA

50

8

4

4

10

1

2

0

NWDA

56

49

52

43

20

12

28

33

ONE

0

0

0

0

0

0

0

0

SEEDA

5

9

13

12

13

0

0

0

SWRDA

A

A

1

0

4

2

4

7

YF

B

28

13

6

4

0

1

0

Projects completed

RDA

2000-01

2001-02

2002-03

2003-04

2004-05

2005-06

2006-07

2007-08

AWM

0

0

3

11

12

18

9

16

EEDA

2

4

9

9

6

6

7

12

EMDA

22

61

71

60

48

52

38

32

LDA

10

12

13

10

8

12

9

5

NWDA

9

15

27

36

36

30

28

36

ONE

23

27

21

21

0

2

0

6

SEEDA

3

2

6

10

0

3

4

6

SWRDA

A

A

2

0

5

3

1

1

YF

B

25

21

21

13

1

2

0

Notes:

1. A new programme management recording system was introduced. To separate out this data would incur disproportionate cost.

2. To separate out this data would incur disproportionate cost.