The current estimated overall cost of delivery of the FiReControl Project for (a) 2004 was £120 million; (b) 2005—£160 million; (c) 2006—£190 million; (d) 2007—£360 million; and (e) 2008—£380 million.
Early estimates of project costs did not include the funding that has been provided to FRAs to support local and regional implementation activity, the costs of the RCC building leases and the costs of equipment that will be installed in every fire station in England to support improved mobilisation.