Spend to date for the whole programme, from inception in 2007 up to 31 December 2009, is £71.7 million.
The total estimated cost of delivering the Immigration Case Work programme is £370 million over the period 2008-09 to 2015-16.
Implementation has commenced with three on-time releases during 2009. The target date to complete all functional components of INTEGRITY is the end of 2013, with full deployment and realisation of benefits expected by 2015.