Skip to main content

Nuclear Submarines: Decommissioning

Volume 506: debated on Wednesday 24 February 2010

To ask the Secretary of State for Defence what recent estimate he has made of the total cost of the interim storage of laid-up submarines project. (318369)

I refer the hon. Member to the answers I gave on 24 November 2009, Official Report, column 54W and on 30 November 2009, Official Report, column 418W.

To ask the Secretary of State for Defence (1) what recent estimate he has made of the whole-life cost of the submarine dismantling project; (318412)

(2) what recent estimate he has made of the cost to the public purse of the submarine dismantling project in (a) Rosyth Dockyard and (b) Devonport Dockyard.

The project currently has approval to undertake a £14 million assessment phase due to complete in 2011. This will be followed by the demonstration phase, which will run from 2011 to 2013; costs for this phase have not yet been approved. Whole life cost figures will be developed as part of the preparation of the main gate business case, which is planned to be submitted for approval in 2013.

The development of the costs associated with different project options, including site options, will form a part of this work.

To ask the Secretary of State for Defence (1) what assessment his Department has made of the merits of using the site at Sellafield for the (a) submarine dismantling and (b) radioactive waste storage elements of the submarine dismantling project; (318414)

(2) what sites his Department is considering to use for the (a) submarine dismantling and (b) radioactive waste storage elements of the submarine dismantling project.

There are currently four regions where there are MOD or defence-related commercial sites that are likely to be considered for submarine dismantling project activities. These regions are Devon, Fife, Argyll and Bute and Berkshire. A number of briefings to elected representatives in these regions have already been carried out, including to the hon. Member, and others have been scheduled.

The project is at an early stage in the process to develop an effective public consultation and associated strategic environmental assessment. This work has included identification of existing nuclear sites, both defence and civil, that are technically capable of submarine dismantling or storing the resultant radioactive waste. At this stage, two sites have been identified that could be technically capable of carrying out dismantling activities and 12 sites have been identified that could be technically capable of carrying out waste storage. Technical capability is only one aspect and the wider suitability of sites has not yet been assessed.

Further analysis work is still required and, until the public consultation is complete, no decisions will be taken on sites for either submarine dismantling or waste storage. I am withholding details of the individual sites identified at this time, as the MOD intend to publish this information in the future as part of the planned public consultation and strategic environmental assessment.

To ask the Secretary of State for Defence what assessment his Department has made of the technical barriers to the (a) submarine dismantling and (b) radioactive waste storage elements of the submarine dismantling project. (318416)

No technical barriers have been identified that would prevent either submarine dismantling or radioactive waste storage from taking place. Most technical aspects of the work have already been demonstrated elsewhere, either in other industry sectors, particularly the civil nuclear sector, or through other countries' work on dismantling nuclear submarines.

We continue to work closely with a range of organisations, including both industry and Government, in the UK and elsewhere, to ensure that we develop appropriate technical solutions that are both safe and effective.