To ask the Minister of State, Department for Transport pursuant to the answer of 4 March 2010, Official Report, column 1363W, on departmental internet, what the cost was of the website redesign. (321924)

The Department for Transport last commissioned a new design for its corporate website in 2005:

www.dft.gov.uk

The work to develop a new information architecture and associated usability testing cost £39,500 (net). The subsequent work to develop a new visual design around the revised information architecture cost £55,825 (net).

To ask the Minister of State, Department for Transport how many designs for its (a) internal website and (b) intranet his Department has commissioned since 2005; and what the cost was of each such design. (321979)

Since 2005 the Department has commissioned one new design for its intranet at a cost of £10,210 (ex VAT). The design work was part of a larger technical upgrade.